125th Street & Dellwood Ridge Street Improvement Project
Project Background:
The 2024 improvement project consists of reconstruction of Heather Avenue N and Upper Heather Avenue N in the Dellwood Ridge Neighborhood and reclamation/overlay of 125th St N from Goodview Avenue to County Road 7.
To sign up for text updates, click on the link below.
https://app2.simpletexting.com/join/joinWebForm?webFormId=6638f506ebc6566c49777641
Project Schedule:
- September 2023- Public Information Meeting
- October 16, 2023- Accept Feasibility Study/Set Public Hearing
- November 20, 2023- Public Hearing/Consider Authorizing Final Design
- November-January 2024- Plan Preparation
- January 2024- Neighborhood Open House with Plans
- February 2024- Accept Plans/Authorize Advertisement for Bids
- March 2024- Open Bids/Award Contract
- June 2024- Start Construction
- September 2024- Complete Construction
- October 2024- Assessment Hearing
*Project Schedule is tentative and subject to change based on weather and contractor progress
Project Scope:
Heather Avenue N and Upper Heather Avenue N-Dellwood Ridge Neighborhood
- Complete Pavement Removal
- Subgrade Correction as Needed
- Installation of Concrete Curb and Gutter
- Installation or Reconstruction of Storm Sewer and Storm Water Management Improvements
125th Street N- Goodview Avenue to County Rd 7
- Recycling the Existing Pavement as Roadway Base
- Minor Subgrade Corrections as Needed
- Minor Grading
- Minor Storm Sewer and Drainage Improvements
- Storm Water Management Improvements
Project Contact:
Liz Finnegan
Senior Engineering Technician
651-762-6316