125th Street & Dellwood Ridge Street Improvement Project

Project Background:

The 2024 improvement project consists of reconstruction of Heather Avenue N and Upper Heather Avenue N in the Dellwood Ridge Neighborhood and reclamation/overlay of 125th St N from Goodview Avenue to County Road 7.

To sign up for text updates, click on the link below. 
https://app2.simpletexting.com/join/joinWebForm?webFormId=6638f506ebc6566c49777641

 

 Project Schedule:

  • September 2023- Public Information Meeting
  • October 16, 2023- Accept Feasibility Study/Set Public Hearing
  • November 20, 2023- Public Hearing/Consider Authorizing Final Design
  • November-January 2024- Plan Preparation
  • January 2024- Neighborhood Open House with Plans
  • February 2024- Accept Plans/Authorize Advertisement for Bids
  • March 2024- Open Bids/Award Contract
  • June 2024- Start Construction
  • September 2024- Complete Construction
  • October 2024- Assessment Hearing

 *Project Schedule is tentative and subject to change based on weather and contractor progress

 Project Scope:

Heather Avenue N and Upper Heather Avenue N-Dellwood Ridge Neighborhood

  • Complete Pavement Removal
  • Subgrade Correction as Needed
  • Installation of Concrete Curb and Gutter
  • Installation or Reconstruction of Storm Sewer and Storm Water Management Improvements

 

125th Street N- Goodview Avenue to County Rd 7

  • Recycling the Existing Pavement as Roadway Base
  • Minor Subgrade Corrections as Needed
  • Minor Grading
  • Minor Storm Sewer and Drainage Improvements
  • Storm Water Management Improvements

 

Project Contact:

Liz Finnegan

Senior Engineering Technician

651-762-6316

lfinnegan@ci.hugo.mn.us