2025 Street Improvement Project (Duck Pass, Long Lake Estates, Ingersoll Avenue)
Construction is anticipated to begin Monday, June 30th with erosion control install and project setup. Main construction work to begin after the 4th of July weekend.
Click here to sign up for project updates
Project Background:
The 2025 Street Improvement Project consists of a roadway reclamation/overlay project within the Duck Pass Neighborhood, Palmes Long Lake Estates Neighborhood and Ingersoll Avenue north of County Rd 7.
Project Schedule:
- October 22, 2024- Public Information Meeting
- November 4, 2024- Accept Feasibility Study/Set Public Hearing
- November 2024- Public Informational Meeting
- December 2, 2024- Public Hearing/Consider Authorizing Final Design
- November-February 2025- Plan Preparation
- January 2025- Neighborhood Open House with Plans
- February 2025- Accept Plans/Authorize Advertisement for Bids
- March 2025- Open Bids/Award Contract
- June 2025- Start Construction
- September 2025- Complete Construction
- October 2025- Assessment Hearing
*Project Schedule is tentative and subject to change based on weather and contractor progress
Project Scope:
- Recycling the Existing Pavement as Roadway Base
- Minor Subgrade Corrections as Needed
- Minor Grading
- Minor Storm Sewer and Drainage Improvements
- Storm Water Management Improvements
- New Asphalt Pavement Surface
Project Contact:
Liz Finnegan
Senior Engineering Technician
651-762-6316