Fable Hills Street Improvement Project

Project Background:
The Fable Hill Street Improvement Project consists of a partial reconstruction of Fable Hill Parkway North from Europa Trail to Elmcrest Avenue and Fable Hill Way North from Fable Hill Parkway N to Fable Hill Parkway N. A mill and overlay project of Fable Hill Circle N, Fable Road N and Fable Road Court N and replacement of the Fable Hill Bridge.


Project Schedule:

  • September 24, 2026- Public Information Meeting
  • October 19, 2026- Council Accept Feasibility Study/Set Public Hearing
  • November 16, 2026- Public Hearing/Consider Authorizing Final Design
  • November-February 2027- Plan Preparation
  • January 2027-Neighborhood Open House with Plans
  • February 2027- Accept Plans/Authorize Advertisement for Bids
  • March 2027- Open Bids/Award Contract
  • June -September 2027- Project Construction
  • October 2027- Assessment Hearing

Project Scope:
Partial Reconstruction:

  • Full Depth Pavement Removal and Replacement
  • Remove and Replace Damaged Curb and Gutter
  • Minor Storm Sewer and Watermain Improvements
  • Full Trail Replacement

Mill and Overlay:

  • Milling of the top 2" of Pavement and Pave
  • Remove and Replace Damaged Curb and Gutter
  • Minor Storm Sewer and Watermain Improvements

Fable Hill Bridge Replacement:

  • New Concrete Beam Bridge

 
Project Contact:
Liz Finnegan
Senior Engineering Technician 
651-762-6316
lfinnegan@ci.hugo.mn.us